Construction well underway
THE construction of new buildings at Cobden Technical School is past the halfway mark, with both staff and students eagerly anticipating the completion of the works.

The construction, which began in January and is due to be finished by mid-December, will see a range of upgraded facilities opening.
“The construction is about 77 per cent complete,” principal Narelle Holliday said.
“They’re building new reception and administration offices, a new conference room and wellbeing space, a new student resource centre library, a new Information Communications Technology (ICT) room and new student toilets.”
Mrs Holliday said a highlight of the construction process was four former Cobden Technical Students working on the new build.
“It’s great that our former students are starting their building careers at Cobden Tech,” she said.
“It’s great that the local employers have seen the value of employing these local young people.
“We’re looking forward to being able to use the space next year.”